Plan around the installation route

Begin with the route from delivery to final position. Doorways, hatches, lifts, corridors and turning space can limit an assembly even when there is plenty of room at its final location.

Show the access constraints on the layout. If a maximum transport or handling size has been established, label it. The layout can then be discussed with sensible breaks between assemblies instead of treating the longest possible section as the automatic goal.

Give every piece a clear identity

Use piece marks that appear on the drawing and the quantity list. Mark the system or area when several similar runs are being ordered. A numbered layout makes it easier to discuss a change without relying on descriptions such as “the second small branch.”

Piece marks are most useful when they identify an orientation too. Label a reference end and show the direction of airflow so the assembled part can be related back to the plan.

Straight rectangular duct sections with formed seams and protective wrapping over the openings.
Straight rectangular duct in several lengths.

Locate taps from a common datum

Dimension each tap or branch from a named end of the main section. Identify whether the dimension is to the centerline or an edge, then show the branch opening and direction.

A top view may be enough for one branch, while branches on different faces need an end or side view. The goal is to make a rotated or mirrored reading of the assembly difficult.

Decide where field connections belong

Show the joints between assemblies and how each end will connect. Consider whether there is enough room at the site to position, align and make the joint after the next piece is installed.

Include access openings, connection hardware or other project details on the layout where they affect assembly. A drawing that shows only duct outlines can hide a connection that becomes inaccessible later.

Round duct taps with rectangular mounting bases, grouped in multiple opening sizes.
Round duct taps with rectangular mounting bases.

Coordinate before releasing the shop drawing

Compare the assembly layout with verified field information and the other work sharing the space. Mark beams, piping, equipment and any opening that controls the route. Resolve revisions on one current drawing rather than spreading changes across old sketches and email photographs.

If a critical connection is not ready to measure, identify it as a field-fit condition for discussion. An unresolved dimension should stay visible as an unresolved item until the installation team can verify it.

A useful prefab package includes

Add quantities and any required grouping by floor, system or area. That gives the shop and installation crew a shared description of the package, rather than a pile of individually correct parts with an unclear assembly plan.

  • A current layout with piece marks, airflow and a named reference end.
  • Opening sizes, section lengths and tap locations with a stated measurement convention.
  • Joint locations, connection details and the intended installation sequence.
  • Maximum assembly dimensions for transport and site access.